Bill 01 May 2025 → 01 Jun 2025
31 days, 563.00 units. Slab limits are pro-rated to 31/30 of the standard limits.
Line items
| Energy charge 0-100 units (103.33 x 4.4300) | 457.77 |
| Energy charge 100-300 units (206.67 x 9.6400) | 1,992.27 |
| Energy charge 300-500 units (206.67 x 13.6100) | 2,812.73 |
| Energy charge >500 units (46.33 x 15.5700) | 721.41 |
| Fixed charge | 134.33 |
| Wheeling charge (563 x 1.1700) | 658.71 |
| Fuel adjustment charge (FAC) (563 x 0.2500) | 140.75 |
| Electricity duty (16%) | 1,106.88 |
| Tax on sale (563 x 0.2604) | 146.61 |
| Rounding | -0.46 |
| Total payable | Rs 8,171.00 |
Units in each slab
| Slab | Units | Rate | Amount |
|---|---|---|---|
| 0-100 | 103.3 | 4.43 | 457.77 |
| 100-300 | 206.7 | 9.64 | 1992.27 |
| 300-500 | 206.7 | 13.61 | 2812.73 |
| >500 | 46.3 | 15.57 | 721.41 |
Against the actual bill
Actual Rs 8,171.00; difference 0.00 (actual minus computed).