Agile flow metrics & Monte Carlo delivery forecasting from issue exports

Download flowcast.zip
Quickstart
unzip flowcast.zip && cd flowcast
uv venv .venv && uv pip install -p .venv/bin/python -e '.[dev]'
.venv/bin/python -m pytest -q

flowcast

Flow metrics and Monte Carlo delivery forecasting straight from your issue tracker export. flowcast answers "when will it be done?" from how your team actually delivers (cycle time, throughput, WIP and aging), with no story points. It reads Jira, Linear and GitHub Projects CSV exports, computes the flow metrics, forecasts with 10,000 Monte Carlo runs, backtests its own past forecasts, and writes a self-contained HTML report with SVG charts.

Features

Install

uv venv .venv && uv pip install -p .venv/bin/python -e '.[dev]'
source .venv/bin/activate   # or call .venv/bin/flowcast directly

Python 3.12+, dependencies: click, rich.

Quickstart

The repo ships generated data in examples/ (regenerate with flowcast generate examples/).

F="examples/jira_export.csv --config examples/workflow.toml --holidays examples/holidays.txt"
flowcast metrics $F
flowcast aging $F
flowcast forecast how-many $F --days 20 --by team
flowcast forecast when $F --by team --split-history
flowcast backtest $F
flowcast report $F -o report.html

Usage

Every command takes the export file plus these common options:

Option Meaning
--profile jira\|linear\|github CSV flavour (default jira)
--changelog FILE Jira changelog CSV (Issue key, Changed, Field, From, To)
--config FILE Workflow mapping TOML (see below); built-in defaults cover common status names
--team T, --type T Filter (repeatable, case-insensitive; --type matches Jira type or Linear/GitHub labels)
--as-of YYYY-MM-DD Pretend today is this date (default: newest event in the data)
--window N History window in calendar days (default 90, 0 = all data)
--holidays FILE, --holiday DATE Holidays to exclude from forecasting history and future days
--include-weekends Treat weekends as working days
--json Machine-readable output

Forecast commands add --runs (10000), --seed (1; same seed gives the same answer) and --by team|epic.

Workflow config

# Maps your tracker's statuses onto the four flow categories.
# active  = someone is working on it (touch time)
# waiting = in progress but idle (queues, blockers); counts against flow efficiency
[workflow]
todo = ["To Do", "Backlog", "Todo"]
active = ["In Progress", "In Review", "Testing"]
waiting = ["Blocked", "Ready for Review", "Ready for QA"]
done = ["Done"]
ignored = ["Canceled"]

[filter]
# types = ["Story", "Bug"]
# teams = ["Atlas"]

Unmapped statuses are an error that lists every offender, so nothing is silently misclassified. Issues whose final status is in ignored (cancelled, duplicate) are dropped.

flowcast metrics

1175 issues, as of 2024-09-30T17:00:00, window 2024-07-03 .. 2024-09-30
finished in window: 407 (6 skipped straight to done, excluded from cycle time)   open: 110   in 
progress: 35

                            Distributions                            
┏━━━━━━━━━━━━━━━━━━━━━━━━━┳━━━━━┳━━━━━━┳━━━━━━┳━━━━━━┳━━━━━━┳━━━━━━━┓
┃                         ┃   n ┃ mean ┃  P50 ┃  P85 ┃  P95 ┃   max ┃
┡━━━━━━━━━━━━━━━━━━━━━━━━━╇━━━━━╇━━━━━━╇━━━━━━╇━━━━━━╇━━━━━━╇━━━━━━━┩
│ cycle time (days)       │ 401 │ 12.0 │  9.0 │ 19.8 │ 29.0 │  55.0 │
│ lead time (days)        │ 407 │ 34.0 │ 25.9 │ 55.3 │ 84.7 │ 144.0 │
│ throughput (items/week) │  13 │ 31.1 │ 28.0 │ 41.2 │ 48.0 │  51.0 │
└─────────────────────────┴─────┴──────┴──────┴──────┴──────┴───────┘

Flow efficiency: 63% (3020 active of 4795 elapsed item-days)
┏━━━━━━━━━━━━━━━━━━┳━━━━━━━━━━━┳━━━━━━━┓
┃ status           ┃ item-days ┃ share ┃
┡━━━━━━━━━━━━━━━━━━╇━━━━━━━━━━━╇━━━━━━━┩
│ In Progress      │      2433 │   51% │
│ Ready for Review │       650 │   14% │
│ Ready for QA     │       529 │   11% │
│ Blocked          │       419 │    9% │
│ Testing          │       294 │    6% │
│ In Review        │       293 │    6% │
└──────────────────┴───────────┴───────┘

Little's Law: avg WIP 49.1 vs throughput x cycle time = 4.46/day x 12.0 d = 53.3 (ratio 0.92, 
consistent)

Cycle time histogram (days)
 0.0 │██████████ 30
 3.2 │█████████████████████ 61
 6.4 │████████████████████████████████████████ 116
 9.6 │██████████████████████ 65
12.8 │██████████████████ 52
16.0 │█████ 15
19.2 │█████████ 25
22.5 │███ 8
25.7 │██ 7
28.9 │██ 7
32.1 │█ 4
35.3 │ 1
38.5 │ 1
41.7 │█ 2
44.9 │█ 2
48.1 │██ 5

Throughput per week
2024-07-01 │███████████████ 19
2024-07-08 │█████████████████████ 27
2024-07-15 │███████████████████████████████ 40
2024-07-22 │████████████████████████████████████████ 51
2024-07-29 │████████████████████████████████████ 46
2024-08-05 │██████████████████████ 28
2024-08-12 │████████████████████████████ 36
2024-08-19 │██████████████████████████ 33
2024-08-26 │██████████████████████████████ 38
2024-09-02 │█████████████ 17
2024-09-09 │████████████████ 21
2024-09-16 │██████████████████ 23
2024-09-23 │████████████████████ 25
2024-09-30 │██ 3
   Arrivals vs departures (last 8 weeks)    
┏━━━━━━━━━━━━┳━━━━━━━━━━┳━━━━━━━━━━━━┳━━━━━┓
┃ week       ┃ arrivals ┃ departures ┃ net ┃
┡━━━━━━━━━━━━╇━━━━━━━━━━╇━━━━━━━━━━━━╇━━━━━┩
│ 2024-08-12 │       14 │         36 │ -22 │
│ 2024-08-19 │       18 │         33 │ -15 │
│ 2024-08-26 │       22 │         38 │ -16 │
│ 2024-09-02 │       16 │         17 │  -1 │
│ 2024-09-09 │       30 │         21 │  +9 │
│ 2024-09-16 │       23 │         23 │  +0 │
│ 2024-09-23 │       20 │         25 │  -5 │
│ 2024-09-30 │        8 │          3 │  +5 │
└────────────┴──────────┴────────────┴─────┘

flowcast aging

Compares the age of each in-progress item with the historical cycle time percentiles: watch above P50, at-risk above P85, critical above P95.

Reference cycle time: P50=9.0d  P85=19.8d  P95=29.0d
┏━━━━━━━━━┳━━━━━━━━┳━━━━━━━━━━━━━━━━━━┳━━━━━━━━━┳━━━━━━━━━━┓
┃ item    ┃ team   ┃ status           ┃ age (d) ┃ risk     ┃
┡━━━━━━━━━╇━━━━━━━━╇━━━━━━━━━━━━━━━━━━╇━━━━━━━━━╇━━━━━━━━━━┩
│ NIM-476 │ Nimbus │ Blocked          │    53.2 │ critical │
│ NIM-545 │ Nimbus │ Blocked          │    26.3 │ at-risk  │
│ ATL-556 │ Atlas  │ Testing          │    21.2 │ at-risk  │
│ NIM-569 │ Nimbus │ In Progress      │    14.3 │ watch    │
│ NIM-572 │ Nimbus │ Testing          │    13.3 │ watch    │
│ ATL-557 │ Atlas  │ Testing          │    13.0 │ watch    │
│ NIM-578 │ Nimbus │ In Progress      │    11.1 │ watch    │
│ NIM-510 │ Nimbus │ Ready for QA     │    11.1 │ watch    │
...

flowcast cfd

 1175 │                                                     ...........
      │                              ..................+++++++#########
      │         ...................++++++++############################
      │..............+++++++###########################################
      │..+++++++++#####################################################
      │################################################################
      │################################################################
      │################################################################
      │################################################################
      │################################################################
      │################################################################
      │################################################################
      └────────────────────────────────────────────────────────────────
       2024-07-03                                            2024-09-30
       # done   + in progress   . to do

flowcast forecast how-many

P85 = 119+ items means 85% of simulated runs finished at least 119 items.

  how-many forecast from 2024-09-30 to 2024-10-28 (20 working   
                             days)                              
┏━━━━━━━━━━━┳━━━━━━━━━━━┳━━━━━━━━━━━━┳━━━━━━━━━━━━┳━━━━━━━━━━━━┓
┃ group     ┃ items/day ┃        P50 ┃        P85 ┃        P95 ┃
┡━━━━━━━━━━━╇━━━━━━━━━━━╇━━━━━━━━━━━━╇━━━━━━━━━━━━╇━━━━━━━━━━━━┩
│ Atlas     │      3.15 │  63+ items │  54+ items │  49+ items │
│ Nimbus    │      3.42 │  68+ items │  59+ items │  55+ items │
│ all teams │      6.56 │ 131+ items │ 119+ items │ 112+ items │
└───────────┴───────────┴────────────┴────────────┴────────────┘
PNN = at least this many items finished in NN% of simulated runs.

Distribution for all teams (items finished):
  89-93 │ 3
  94-99 │█ 31
100-104 │███ 114
105-110 │██████ 265
111-115 │████████████████ 698  <- P95
116-121 │████████████████████████ 1028  <- P85
122-126 │████████████████████████████████████████ 1715
127-132 │██████████████████████████████████████ 1622  <- P50
132-137 │█████████████████████████████████████ 1576
138-142 │█████████████████████████████████ 1403
143-148 │██████████████████ 772
149-153 │███████████ 486
154-159 │████ 166
160-164 │██ 91
165-170 │ 21
171-175 │ 9

flowcast forecast when

--items N forecasts a specific number; without it the open backlog (everything not done) is used. --split-rate 1.0-1.3 multiplies the backlog by a uniformly drawn factor in each run; --split-history bootstraps the factor from how much each historical epic grew relative to the scope created in its first 14 days. With --by team the total is the date the last team finishes. With --by epic each epic is forecast against the whole group's throughput, and the total assumes epics are done one after another.

                                   when forecast from 2024-09-30                                    
┏━━━━━━━━━━━━━━━━━━┳━━━━━━━━━┳━━━━━━━━━━━┳━━━━━━━━━━━━━━━━━━┳━━━━━━━━━━━━━━━━━━━┳━━━━━━━━━━━━━━━━━━┓
┃ group            ┃ backlog ┃ items/day ┃              P50 ┃               P85 ┃              P95 ┃
┡━━━━━━━━━━━━━━━━━━╇━━━━━━━━━╇━━━━━━━━━━━╇━━━━━━━━━━━━━━━━━━╇━━━━━━━━━━━━━━━━━━━╇━━━━━━━━━━━━━━━━━━┩
│ Atlas            │      55 │      3.15 │       2024-11-08 │ 2024-11-15 (+34d) │       2024-11-21 │
│                  │         │           │           (+29d) │                   │           (+38d) │
│ Nimbus           │      55 │      3.42 │       2024-11-06 │ 2024-11-12 (+31d) │       2024-11-18 │
│                  │         │           │           (+27d) │                   │           (+35d) │
│ all teams (last  │     110 │         - │       2024-11-11 │ 2024-11-18 (+35d) │       2024-11-21 │
│ to finish)       │         │           │           (+30d) │                   │           (+38d) │
└──────────────────┴─────────┴───────────┴──────────────────┴───────────────────┴──────────────────┘
PNN = NN% of simulated runs finished on or before this date.
Scope uncertainty: backlog x historical epic growth (median 1.62, max 2.06)

Distribution for all teams (last to finish) (working days needed):
21-22 │█ 29
23-24 │████ 200
24-25 │█████████████████ 873
26-27 │███████████████ 810
28-29 │███████████████████████████████████████ 2058
30-30 │████████████████████████████████████████ 2114  <- P50
32-32 │███████████████████████████████ 1616
33-34 │██████████ 531
35-36 │████████████████ 854  <- P85
37-38 │█████████ 481  <- P95
38-39 │█████ 244
40-41 │█ 77
42-43 │█ 76
44-44 │ 26
46-46 │ 7
47-48 │ 4

flowcast backtest

Replays "how many items in the next N working days" from weekly past origins using only data available then, and checks how often reality met each confidence level. A calibrated forecaster is met about 50% / 85% / 95% of the time. The first months of the sample dataset are a ramp-up from an empty system, which the backtest honestly shows as under-forecasting.

  Backtest: items finished in the next 20 working days   
┏━━━━━━━━━━━━┳━━━━━━━━━━━━┳━━━━━━┳━━━━━━┳━━━━━━┳━━━━━━━━┓
┃     origin ┃      until ┃ P95+ ┃ P85+ ┃ P50+ ┃ actual ┃
┡━━━━━━━━━━━━╇━━━━━━━━━━━━╇━━━━━━╇━━━━━━╇━━━━━━╇━━━━━━━━┩
│ 2024-04-01 │ 2024-04-29 │   60 │   67 │   79 │    148 │
│ 2024-04-22 │ 2024-05-20 │   88 │   94 │  107 │    123 │
│ 2024-05-13 │ 2024-06-11 │   95 │  101 │  114 │    135 │
│ 2024-06-03 │ 2024-07-02 │  101 │  108 │  121 │    113 │
│ 2024-06-24 │ 2024-07-23 │  108 │  115 │  127 │    139 │
│ 2024-07-15 │ 2024-08-12 │  111 │  117 │  129 │    166 │
│ 2024-08-05 │ 2024-09-03 │  119 │  126 │  139 │    136 │
│ 2024-08-26 │ 2024-09-24 │  121 │  127 │  138 │     98 │
└────────────┴────────────┴──────┴──────┴──────┴────────┘
P50: actual >= forecast in 62% of 8 origins (calibrated would be about 50%)
P85: actual >= forecast in 88% of 8 origins (calibrated would be about 85%)
P95: actual >= forecast in 88% of 8 origins (calibrated would be about 95%)
Median forecast error (P50 vs actual): 20%

flowcast report

flowcast report $F -o report.html writes one self-contained HTML file (inline CSS and SVG, no JavaScript, light and dark themes). Pass --split-rate to include scope growth in the backlog forecast.

Architecture

Module Role
importers.py CSV profiles to Issue objects (transitions, labels, team, epic)
workflow.py Status mapping and TOML config
timeline.py Transitions to segments; start, done, cycle/lead/age; reopens and skips
dataset.py Load, validate, filter, build timelines as of a date (Context)
metrics.py Percentiles, throughput, CFD, aging, flow efficiency, Little's Law
forecast.py Monte Carlo simulation, confidence tables, split rate
analysis.py Per-team / per-epic forecast orchestration and JSON shaping
backtest.py Rolling-origin forecast scoring
calendar.py Working days and holidays
ascii.py, svg.py, report.py Terminal charts, SVG primitives, HTML report
generate.py Synthetic export generator
cli.py Click commands

See docs/design.md for the algorithms with worked examples.

Tests

.venv/bin/pytest -q

46 tests cover timeline construction (reopens, skipped statuses, truncation), metric formulas, CFD consistency, Monte Carlo reproducibility and convergence, backtesting, the three CSV profiles and the CLI.

Limitations